Current status of project:
- We are in the stage of transitioning from background research into actual product/software design and testing.
Work completed in the last week:
- We have completed background research, investigated prior art and patents, created a list of product specifications, and written a draft for the preliminary report due Wednesday. Through the literature search, we have developed stronger support for the uniqueness and marketability of our product. We have written a short sample of code and verified the viability of a software program to diagnose cardiac arrhythmias from an ECG.
Work planned for next week:
- Create our website.
- Begin to test viability of our product specifications to address potential problems, ie. power consumption.
- Conduct further research into signal analysis, and implement into software.
- Begin preliminary designs of hardware.
Anything needed from mentor/client or TA or instructor to continue work:
- From Dr. Anastasio: We would like to confirm the grading criteria for our project, which contains both software and hardware components. We would like to receive feedback on whether we should invest our efforts in just the software (or just the hardware) for grading and time purposes.